MoEFCC Notification S.O. 5481(E) (2021)
Legally mandates fly-ash bricks/blocks for all construction within 300 km of coal-based power plants.
Judicial decisions establishing mandatory fly ash utilisation within 300 km of thermal plants.
Key Holding: Confirmed mandatory 25% fly ash mixing in bricks within 50 km. Brick makers cannot reject fly ash on cost grounds.
Key Holding: TPPs must use 100% of generated fly ash. Strict action for non-compliance. Polluter pays principle.
Key Holding: Fly-ash bricks mandatory unless cost exceeds CPWD/PWD schedule rates.
Legally mandates fly-ash bricks/blocks for all construction within 300 km of coal-based power plants.
Fly-ash bricks mandatory unless price exceeds CPWD/PWD schedule rates.
The 2024 amendment expands and clarifies the compliance framework. It expressly covers Central, State and Local authorities, Govt. undertakings, other Govt. agencies and all private agencies for building construction projects within 300 km, subject to the stated Schedule of Rates condition.
It also requires local authorities to make provisions in building bye-laws and other relevant regulations for the use of ash and ash-based products, and introduces written-notice and ash-reservation provisions relevant to thermal power plants and ash-based product manufacturers.
If you have information concerning a project, agency or other entity that appears not to be following the applicable notification, you can inform FAIFG for guidance and reporting support.
| Violation Type | Applicable Penalty | Legal Clause |
|---|---|---|
| TPP non-utilisation of ash | ₹1000 per ton | Clause C(1) |
| Builder avoids fly ash products | ₹75 per sq.ft | Clause C(3) proviso |
| Illegal clay brick usage/kiln | ₹1500/ton + sealing | Clause B(8), C(4) |