Judicial decisions establishing mandatory fly ash utilisation within 300 km of thermal plants.

Compliance position: The purpose of this page is to make the mandatory character of the applicable Gazette provisions clear. Where the notification applies, avoiding the prescribed use of ash-based products is not merely a commercial preference; it can constitute non-compliance with the applicable environmental notification.
Judicial decision

Tamil Nadu Fly Ash Brick & Block Mfrs. Ass'n v. UOI

Madras HC, 28 Jan 2015(2015) (T.S. Sivagnanam, J.)
"No person shall within a radius of fifty kilometers... manufacture clay bricks without mixing at least 25% of ash"

Key Holding: Confirmed mandatory 25% fly ash mixing in bricks within 50 km. Brick makers cannot reject fly ash on cost grounds.

NGT

Shantanu Sharma v. Union of India

NGT (PB), 12 Feb 2020O.A. No. 117/2014
"NGT directed comprehensive utilization and scientific disposal of 100% fly ash by all Thermal Power Plants."

Key Holding: TPPs must use 100% of generated fly ash. Strict action for non-compliance. Polluter pays principle.

NGT

K. Saravanan v. MoEFCC

NGT (SZ), 28 Apr 2025O.A. No. 74/2021
"S.O.5481(E) mandates 100% ash utilization by power plants with penalties for non-compliance."

Key Holding: Fly-ash bricks mandatory unless cost exceeds CPWD/PWD schedule rates.

Statutory Framework

2021

MoEFCC Notification S.O. 5481(E) (2021)

"All building construction projects within 300 km shall use ash bricks or ash based products"

Legally mandates fly-ash bricks/blocks for all construction within 300 km of coal-based power plants.

2022

Amendment S.O. 6169(E) (2022)

"Replaced 'higher than price of alternative products' with 'more than price mentioned in CPWD Schedule'"

Fly-ash bricks mandatory unless price exceeds CPWD/PWD schedule rates.

2024

Amendment S.O. 05(E) (2024)

The 2024 amendment expands and clarifies the compliance framework. It expressly covers Central, State and Local authorities, Govt. undertakings, other Govt. agencies and all private agencies for building construction projects within 300 km, subject to the stated Schedule of Rates condition.

It also requires local authorities to make provisions in building bye-laws and other relevant regulations for the use of ash and ash-based products, and introduces written-notice and ash-reservation provisions relevant to thermal power plants and ash-based product manufacturers.

Compliance contact

Report Suspected Non-Compliance

If you have information concerning a project, agency or other entity that appears not to be following the applicable notification, you can inform FAIFG for guidance and reporting support.

Report / Seek Guidance

Environmental Compensation Matrix

Violation TypeApplicable PenaltyLegal Clause
TPP non-utilisation of ash₹1000 per tonClause C(1)
Builder avoids fly ash products₹75 per sq.ftClause C(3) proviso
Illegal clay brick usage/kiln₹1500/ton + sealingClause B(8), C(4)
For agencies and private parties: If the Gazette requirement applies to your project, the existence of a cheaper conventional alternative does not by itself remove the statutory requirement. The applicable price condition and other provisions must be checked against the Gazette.